On March 1, 2021, the U.S. District Court for the Southern District of Ohio issued a ruling denying in part the summary judgment motion of Defendants Ingersoll-Rand and Trane U.S., against whom Plaintiff FIP Realty Co. brought various claims related to the historic release of VOCs on a site now owned by Plaintiff. See Fip Realty Co. v. Ingersoll-Rand Plc, No. 2:19-cv-03291. After acquiring the site out of receivership in 2010, Plaintiff retained several environmental consulting firms and undertook voluntary remediation efforts pursuant to the Ohio Voluntary Action Program (VAP). Six years later Plaintiff submitted a No Further Action (NFA) letter to the Ohio EPA, which in turn issued a Final Order and Covenant releasing Plaintiff from liability at the site as a result of its successful remediation. In 2019 Plaintiff filed the instant lawsuit seeking to recover remediation costs under CERCLA Sections 107(a) and 113(f)(3)(B), and to obtain a declaratory judgment under Section 113(g)(2) that Defendants are liable for all future costs. Defendants moved for summary judgment on various issues, two of which are the subject of disagreement among the federal appellate courts. Read More »

The First Circuit recently affirmed the District of Rhode Island’s approval of a superfund consent decree entered into between the United States Environmental Protection Agency (“EPA”), the State of Rhode Island and several Potentially Responsible Parties despite opposition by third party PRPs that the settlement was arbitrary and capricious and contrary to the Comprehensive Environmental Response, Compensation, and Liability Act (“CERCLA”). Emhart Indus., Inc. v. CNA Holdings LLC, No. 19-1563, slip op. (1st Cir. 2021 Feb. 17, 2021). What makes this case unique, and bolstered the arguments of the objectors, is that the settlement incorporated work pursuant to a ROD that the District Court had already determined has not been selected in accordance with law. Nevertheless, both the District Court and the First Circuit held that the finding did not preclude the settlement, leaving the objectors exposed to contribution claims for a remedy potentially inconsistent with the National Contingency Plan (“NCP”). In affirming the lower court, the First Circuit highlighted the “integral part” that early settlement plays in CERCLA’s statutory scheme, thus giving deference to the settling parties. Read More »

On December 10, 2020, Christmas came early for the federal government. In United States v. Shell Oil Company (CV 91-00589-CJC), the Central District of California awarded it nearly $50 million in costs to remediate waste generated by oil companies that produced World War II aviation fuel at the McColl Superfund Site in Fullerton, California. Though their liability had already been established in a 1993 Second Circuit decision, the companies sought to raise triable issues of fact on damages, and they also contended that the government’s statutory basis under CERCLA was improper. But the Court rejected these arguments and granted the government’s motion for summary judgment. Read More »

On August 19, 2020, the United States District Court for the Southern District of Texas issued what it hoped was “the third, and should be the last, opinion in these environmental pollution cases arising from World War II and the Korean War.” Exxon Mobil Corp. v. United States, Nos. H-10-2386 & H-11-1814, slip op. at 1 (S.D. Tex. Aug. 19, 2020). The court’s decision provides a unique window into an allocation for recovery under the Comprehensive Environmental Response, Compensation and Liability Act (“CERCLA”), a process more often conducted in private alternative dispute arrangements among potentially liable parties. Read More »

In a split decision that could have ramifications for future lawsuits involving the present pandemic, a majority panel in the Ninth Circuit held that the United States was not liable under CERCLA as an “operator” at the Lava Cap Mine Superfund Site when it ordered the mine to shut down during World War II. United States v. Sterling Centrecorp Inc., No. 18-15585 (9th Cir. Oct. 5, 2020). The decision will likely spell some relief for local, state, and federal officials that have issued similar shutdown orders across the United States during the COVID-19 pandemic. Read More »

On September 14, 2020, the U.S. Court of Appeals for the Ninth Circuit held that speculative, potential future response costs are not recoverable in a contribution action under CERCLA, even if the party seeking contribution has already made an expenditure for such costs pursuant to a settlement. The response costs at issue in ASARCO LLC v. Atlantic Richfield Co, No. 18-35934, D.C. No. 6:12-cv-00053-DLC (9th Cir. Sept. 14, 2020) were part of a cash-out bankruptcy settlement that resolved plaintiff ASARCO LLC’s liability for several contaminated sites. Only a portion of the settlement funds paid by ASARCO had been spent on remediating the site in question, with the rest held in trust to address future potential response costs. Although the Ninth Circuit affirmed the district court’s allocation of 25 percent of the cleanup responsibility to the defendant, Atlantic Richfield, it vacated and remanded the district court’s decision with respect to the future costs. Read More »

Last week the Third Circuit held that Combustion Equipment Associates, Inc. n/k/a Carter Day Industries, Inc. (“Carter Day”) was not protected from a contribution claim brought by Compaction Systems Corporation of Connecticut, Inc. and Compaction Systems Corporation (collectively, “Compaction”) for amounts Compaction was obligated to pay to the United States despite Carter Day having resolving its liability to the State of New Jersey for the same site. New Jersey Department of Environmental Protection v. American Thermoplastics Corporation, et al., Nos. 18-2865 & 19-2243 (3d. Cir. Sept. 8, 2020). At issue was whether the settlement agreement between Carter Day and the New Jersey Department of Environmental Protection (“NJDEP”) addressed the same “matter” as the contribution claim brought by Compaction for response costs at the Combe Fill South Landfill Superfund Site (the “Combe Fill Site” or “Site”). Read More »

Earlier this week the Eleventh Circuit issued a published decision in Pinares v. United Technology Corporation, No. 18-15104, slip op. (11th Cir. Aug. 31, 2020), affirming the United States District Court for the Southern District of Florida’s grant of summary judgment in favor of Pratt & Whitney, dismissing the plaintiffs’ claims as time-barred. In doing so, the Court held that the personal injury tolling provision in the Comprehensive Environmental Response, Compensation and Liability Act (“CERCLA”) does not apply to public liability actions brought pursuant to the Price-Anderson Act (“PAA”) or to claims styled under state law based on injuries from radiation exposure. Thus, the lawsuit pursued by Joselyn and Steve Santiago alleging that Pratt & Whitney was liable for their deceased daughter Cynthia Santiago’s cancer was time barred. Read More »

On August 10, 2020, the Ninth Circuit reversed a lower court’s grant of defendants’ motion for summary judgement, permitting plaintiffs’ case to move forward in a Superfund action for contribution. See Arconic v. APC Investment, No. 19-55181 (9th Cir. Aug. 10, 2020), a case we had reported on here. At issue was whether a settlement between plaintiffs and certain de minimis parties for future potential response costs was an adequate triggering event for the statute of limitations period (against different defendants) in an action for contribution under CERCLA Section 113(f). The Ninth Circuit held that it was not, explaining that in the context of a “judicially approved settlement,” the proper triggering event was a settlement which imposed actual cleanup costs in excess of a party’s estimated liability at the site. Read More »

The D.C. Circuit recently held that EPA was not required to consider mitigation measures taken at a site when determining whether to add the site to the National Priorities List (“NPL”) under CERCLA. Meritor, Inc. v. EPA, No. 18-1325, 2020 WL 4299124 (D.C. Cir. July 28, 2020).

In 2016, the U.S. Environmental Protection Agency (“EPA”) conducted a study of indoor air quality at the Rockwell International Wheel & Trim facility (the “Site”), located in Mississippi, and discovered elevated concentrations of toluene, trichloroethylene (“TCE”), and cis-1,2-dichloroethene (“DCE”) in the main building at the Site. In 2017, Meritor, Inc. (“Meritor”), which inherited liability for contamination at the Site, conducted a subsurface investigation beneath the main building and uncovered elevated levels of toluene and TCE. In that same year, Meritor installed a sub-slab depressurization system designed to mitigate the impacts of vapor intrusion in the main building. In 2018, notwithstanding Meritor’s mitigation efforts, EPA added the Site to the NPL based on vapor intrusion impacts. Read More »