Showing 77 posts in Remediation.

On August 19, 2020, the United States District Court for the Southern District of Texas issued what it hoped was “the third, and should be the last, opinion in these environmental pollution cases arising from World War II and the Korean War.” Exxon Mobil Corp. v. United States, Nos. H-10-2386 & H-11-1814, slip op. at 1 (S.D. Tex. Aug. 19, 2020). The court’s decision provides a unique window into an allocation for recovery under the Comprehensive Environmental Response, Compensation and Liability Act (“CERCLA”), a process more often conducted in private alternative dispute arrangements among potentially liable parties. Read More »

On September 14, 2020, the U.S. Court of Appeals for the Ninth Circuit held that speculative, potential future response costs are not recoverable in a contribution action under CERCLA, even if the party seeking contribution has already made an expenditure for such costs pursuant to a settlement. The response costs at issue in ASARCO LLC v. Atlantic Richfield Co, No. 18-35934, D.C. No. 6:12-cv-00053-DLC (9th Cir. Sept. 14, 2020) were part of a cash-out bankruptcy settlement that resolved plaintiff ASARCO LLC’s liability for several contaminated sites. Only a portion of the settlement funds paid by ASARCO had been spent on remediating the site in question, with the rest held in trust to address future potential response costs. Although the Ninth Circuit affirmed the district court’s allocation of 25 percent of the cleanup responsibility to the defendant, Atlantic Richfield, it vacated and remanded the district court’s decision with respect to the future costs. Read More »

Last week the Third Circuit held that Combustion Equipment Associates, Inc. n/k/a Carter Day Industries, Inc. (“Carter Day”) was not protected from a contribution claim brought by Compaction Systems Corporation of Connecticut, Inc. and Compaction Systems Corporation (collectively, “Compaction”) for amounts Compaction was obligated to pay to the United States despite Carter Day having resolving its liability to the State of New Jersey for the same site. New Jersey Department of Environmental Protection v. American Thermoplastics Corporation, et al., Nos. 18-2865 & 19-2243 (3d. Cir. Sept. 8, 2020). At issue was whether the settlement agreement between Carter Day and the New Jersey Department of Environmental Protection (“NJDEP”) addressed the same “matter” as the contribution claim brought by Compaction for response costs at the Combe Fill South Landfill Superfund Site (the “Combe Fill Site” or “Site”). Read More »

The Federal Tort Claims Act permits claims for monetary damages against the United States for injury or loss of property caused by the wrongful acts of federal employees. See 28 U.S.C. § 1346(b)(1). However, this waiver of sovereign immunity is limited by the discretionary function exception, which preserves immunity for claims “based upon the exercise or performance or the failure to exercise or perform a discretionary function or duty on the part of a federal agency or an employee of the Government.” 28 U.S.C. § 2680(a). Recently, the United States Court of Appeals for the Ninth Circuit analyzed the discretionary function exception in the context of environmental contamination, finding that the exception does not apply to what can best be described as ordinary negligence in the performance of a site remediation. Nanouk v. United States, No. 13-35116 (Sept. 4, 2020). Read More »

In late July 2020, the United States District Court for the Southern District of Ohio granted in part and denied in part defendants’ motion to dismiss in a case involving releases of uranium radiation and other non-radioactive waste onto plaintiffs’ property. See Op. and Order, McGlone v. Centrus Energy Corp., et al., Case No. 2:19-cv-02196 (S.D. Ohio, July 31, 2020). Claims involving the Comprehensive Environmental Response, Compensation, and Liability Act (“CERCLA”) and the Price-Anderson Act and were dismissed for failing to state a claim, while most state law tort claims for releases of non-radioactive waste were permitted to move forward, the court clarifying that medical monitoring exists as a form of damages under Ohio law and not as a separate claim. Read More »

In MPM Silicones, LLC v. Union Carbide Corporation, the U.S. Court of Appeals for the Second Circuit held that there can be more than one “remedial action” at a site under certain circumstances for the purpose of determining the statute of limitations under CERCLA. Dkt. No. 17-3468(L), 17-3669(XAP) (2d Cir. 2019). The decision clarified a statement in a prior decision by the Second Circuit that had suggested otherwise. Read More »

On May 4, 2020, the Third Circuit issued a precedential opinion affirming the United States District Court for the District of New Jersey’s decision that the United States Government (the “Government”) is not liable as an operator under the Comprehensive Environmental Response, Compensation and Liability Act (“CERCLA”) for its involvement at a chromite ore processing plant in New Jersey during World Wars I and II. PPG Indus. Inc. v. United States, No. 19-1165, slip op. (3d Cir. May 4, 2020). The decision clarifies the applicable standard for parties seeking to hold the Government liable as an operator for cleanup costs at contaminated former defense sites. Read More »

In a highly anticipated decision, on April 20, 2020, the U.S. Supreme Court ruled that state courts may award restoration damages to landowners who seek, under state law, a more expensive cleanup than that selected by EPA, but as potentially responsible parties under CERCLA they must first receive EPA’s approval of their alternative cleanup plan before they would be entitled to those damages. Atlantic Richfield Co. v. Christian, et al., No. 17-1498 (U.S. Apr. 20, 2020). Beyond its fact-specific holding, the opinion’s broader implications may have a significant impact on CERCLA cleanups and litigation going forward.   Read More »

In Frazer/Exton Development, L.P. v. United States, the United States Court of Appeals for the Federal Circuit affirmed the dismissal of a takings claim against the federal government relating to environmental contamination because the appellants, current and former landowners of the site at issue, filed their lawsuit more than 6 years after environmental remediation was complete. Frazer/Exton Development, L.P. v. United States, No. 2019-2143 (Fed. Cir. Apr. 7, 2020). Read More »

It has been more than a decade since the United States Supreme Court decided Burlington Northern & S.F. R. Co. v. United States, 129 S. Ct. 1870 (2009), holding that liability under Section 107(a) of CERCLA is not necessarily joint and several, but in appropriate circumstances can be divisible. And yet, courts still struggle to determine when liability is divisible and thus subject to apportionment rather than equitable allocation, with the latter, joint and several liability, still remaining the go to default. The March 30, 2020 decision from the U.S. District Court for the Southern District of Indiana, in the case of Von Duprin, LLC v. Moran Electric Service, Inc., No. 1:16-cv-01942-TWP—DML (S.D. Ind. Mar. 30, 2020), is no exception. The Court found that liability for a comingled plume of volatile organic compounds (“VOCs”) was divisible, but then applied equitable factors to allocate liability. And, in getting to its final decision, the Court also discussed what costs can be recovered under 107(a), the standard for determining compliance with the National Contingency Plan (“NCP”), and what steps a lessee needs to take to avail itself of the bona fide prospective purchaser (“BFPP”) defense. This is going to be a long one, so pull up a chair. Read More »